Re: HA Setup Review

Поиск
Список
Период
Сортировка
От akshay polji
Тема Re: HA Setup Review
Дата
Msg-id CAHecRenvdNu3-HZ=Ym42pajjWbu9NqWDHscHFxrfjvvpacgd6g@mail.gmail.com
обсуждение исходный текст
Ответ на Re: HA Setup Review  (Scott Ribe <scott_ribe@elevated-dev.com>)
Ответы Re: HA Setup Review  ("Deepak Pahuja ." <deepakpahuja@hotmail.com>)
Список pgsql-admin
"All cloud providers have downtime and outages. Maybe this is reliable enough for you, but just don't treat it as a guarantee." --> Very true!! 

"if a network glitch, or failure of a replica, can cascade to cause failure of primary, is that really HA?" --> Absolutely not. 
But then for HA you need a replica, so now the question is if you want to do Async or Sync. 
Sync would mean impact to Primary due to n/w issues or failures but guarantee no-to-minimum data loss, 
Async would mean no impact to Primary due to n/w issues or failures but can cause data loss due to replication lag. 
If you ask the applications, they will need both .. Neither impact to primary nor data loss. How to weigh the options in this case? 

Unless there's a middle ground that I am not aware of but would love to know more. 

Thanks,
Akshay 

On Tue, Apr 30, 2024 at 10:08 PM Scott Ribe <scott_ribe@elevated-dev.com> wrote:
> On Apr 30, 2024, at 10:29 AM, akshay polji <akshay.polji@gmail.com> wrote:
>
> So do you think that even such a cluster with 3 node pgpool + postgresql (running on the same machine)  Synchronous Replication (Any one out of the two replicas) would mean Primary DB will be at risk of degraded performance?

All cloud providers have downtime and outages. Maybe this is reliable enough for you, but just don't treat it as a guarantee. The point is: if a network glitch, or failure of a replica, can cascade to cause failure of primary, is that really HA?

В списке pgsql-admin по дате отправления:

Предыдущее
От: Scott Ribe
Дата:
Сообщение: Re: HA Setup Review
Следующее
От: Ramiro Sanchez
Дата:
Сообщение: Re: Installation of PostGIS without internet or with limited internet access